Any person who intends to carry out the demolition of a building over 1750 cubic feet (approximately 50 cubic metres), must inform the local authority in writing, at least six weeks prior to commencement.
You should complete a demolition notice proforma with details of your intended demolition and send to us.
The completed notice must be submitted along with a location plan of the building showing adjacent streets and buildings. You should also send a copy of this notice to any adjacent building occupiers, and service providers such as gas, electricity and water suppliers.
Once we receive your notice, a member of the Building Control Team may visit the site to identify any conditions or risks that need to be taken into account and to confirm which persons or organisations will be notified of the works.
A counter notice will then be sent to the person intending to carry out the demolition detailing any conditions the council requires them to adhere to when carrying out works. A copy of the notice will also be sent to the owner or occupier of adjacent premises, statutory undertakers and other interested parties as necessary.
Demolition may legally commence after the council has issued its counter notice, or six weeks after notice was issued upon the council, whichever occurs first.
There is no charge for the demolition notice process.
Yes, the following do not require a notice to be made:
Other legislation may require you to inform others before demolition work is to commence, this may include but is not limited to the following (These are outside the scope of an intent of demolition notice made to the Council):
Demolition notice online proforma